Standing 180 metres above George Street, Grosvenor Place is one of Sydney’s landmark office developments, with sustainability woven into its story from the start.

Designed by renowned architect Harry Seidler, the 44-level tower is an icon of Sydney’s commercial landscape.

Today, the building supports a large daily workforce, and delivering hot water efficiently and reliably to building amenities and end-of-trip facilities is central to its sustainability performance.

Like many established commercial buildings, Grosvenor Place is undertaking a broader program of updates to support electrification, reducing reliance on gas while maintaining efficient and reliable services.

As part of this program, Rheem was engaged to improve overall system efficiency, reduce energy consumption and support Grosvenor Place’s environmental performance targets.

The project retrofitted and upgraded the existing centralised gas-fired domestic hot water system, advancing the building’s sustainability goals while maintaining the reliable supply expected in a premium commercial environment.

The challenge: Balancing demand, efficiency and performance

What was once a traditional commercial office tower now supports a broader range of workplace amenities designed to meet the changing needs of approximately five thousand occupants.

Understanding the facility’s anticipated peak hot water demand and broader operational requirements was a critical first step in the upgrade process. To inform the design, Rheem reviewed how hot water was used across the building and the performance requirements of the existing system.

The assessment needed to balance multiple objectives, including improved energy efficiency, sustainability outcomes and long-term operational performance. The solution would also need to accommodate plant room constraints and future serviceability considerations while supporting the building’s ongoing needs.

The current end-of-trip facilities, with 31 shower cubicles, grooming stations, restaurant toilets and DDA facilities, were designed to support the growing number of people choosing to cycle, run or walk to work. These facilities place significant demand on the building’s hot water infrastructure.

The solution: A collaborative approach to delivery

Throughout the full project lifecycle, Rheem remained actively involved, starting with early-stage design consultation and coordination with engineers and hydraulic contractors. This continued through equipment supply, installation support, commissioning and final project delivery.

Working closely with VAE Group, the project team reviewed plant room requirements, installation access and future serviceability considerations to support a smooth delivery. The team also provided site-specific technical guidance throughout the installation of the new system.

To identify the most appropriate solution, Rheem assessed the facility’s anticipated peak hot water demand and broader operational requirements.

Based on this, a tailored system comprising two 30kW YF Series Commercial Heat Pumps, three 1,000-litre RT Series storage tanks and three 15kW Commercial Heating Units was developed.

The heat pump-based solution was selected to support the building’s sustainability and energy efficiency objectives. Compared with other systems, heat pump technology offers a more energy-efficient approach, helping reduce energy consumption while supporting long-term operational performance.

The result was a high-efficiency hot water solution designed to meet the building’s operational requirements while supporting broader sustainability objectives. Through collaboration between all stakeholders, the project successfully balanced performance, reliability and long-term operational outcomes.

A sustainable hot water system designed to electrify critical infrastructure at landmark Sydney CBD Building Grosvenor Place.
Rheem Commercial Hot Water Solution at landmark Sydney CBD building.

Delivering operational and sustainability outcomes

By adopting heat pump technology, the project moved away from the existing gas-fired plant and towards a more energy-efficient solution. The YF Series heat pumps achieve a coefficient of performance (COP) of up to 4.23 under standard operating conditions, supporting the building’s energy-efficiency objectives.

The system combines heat pump technology with approximately 3,000 litres of insulated hot water storage to support operational demand while minimising standing heat losses.

Intelligent controls and building management system integration also provide facilities teams with improved visibility of system performance, helping support ongoing operational management.

The inclusion of multiple storage vessels and supplementary heating units provides additional resilience during maintenance activities or periods of increased demand, helping to uphold continuity of service across the building.

The Grosvenor Place upgrade demonstrates the importance of aligning system design with building performance goals, site constraints and long-term operational needs.

The project provides a practical example of how heat pump technology can be integrated into existing assets while maintaining reliability and supporting sustainability objectives. It also reflects Rheem Commercial’s experience delivering complex hot water solutions across demanding commercial environments.